Installation and Commissioning of Cryogenic Nitrogen Unit

Client: Petrochemical Plant

Location: Basrah Khor Al Zubair

Scope:

  • installation of Cryogenic Nitrogen Unit including two air compressors, dryers, refrigeration unit, water circulation pumps and separation tower.

  • commissioning and running the unit and produce Nitrogen according to manufacturer specification.

Baghdad Electrical Power Station (3000MW)

Client: Mass Energy Group Holding (MGH)

Client’s Engineer: APPA consult GmbH

Vendor: Petrogas-Gas Systems BV

Location: Besmaya

Status: on-going

Scope:

  • supervision of installation of gas conditioning equipment.

  • testing.

  • calibration.

  • startup & commissioning.

Gas Compressor Station – EPC

Client: Basrah Gas Company (BGC)

Location: South Rumaila, Markazya and Shamya Degassing Stations, Basrah

Scope:

  • engineering.

  • procurement.

  • packaging.

  • installation.

  • start-up.

  • commissioning of 4 gas booster blowers. 

Erection Supervision, Commissioning & Start-Up of
Atlas Copco 6-Stage Compressor

Machine: GT056L3K1/021L3K1

Client: SIAD Macchine Impianti S.p.A.

Vendor: Atlas Copco Energas

End User: Sulaymaniya Steel Factory, MASS Group Holding

Scope:

  • erection supervision.

  • commissioning & start-up.

 

Specifications:

  • 6 stages / 2 sections. 

  • MAC 34500 Nm3/h@11 bar.

  • BAC 9800Nm3/h@44 bar.

  • driving motor 5600KW.

Inspection of Critical Electrical Equipment at UmQasrStorage Terminal

Client: Basrah Gas Company (BGC) 

Location: UmQasr

 

 

Scope:

  • inspection of existing critical electrical equipment installed at Storage Terminal and Marine Terminal.

  • assessment:recommendations regarding the need for repair, refurbishment/replacement of equipment.

  • rehabilitation.

 

Rehabilitation Project UmQasr

Client: Sajer Basrah

Location: UmQasr

 

 

Scope:

  • inspection of cryogenic tank.

 

Test & Transformer Oil Purification

Client: Weatherford

Location: Zubair & Rafidiya Site

 

 

Scope:

  • test.

  • oil purification.

Nitrogen Plant 

Client: IT-Netze

End User: State Company for Petrochemical Industries (SCPI)

Location: Basrah

Scope:

  • civil works.

  • installation of equipment.

  • fabrication and welding all interconnection piping.

  • x-ray testing and hydro testing of welding joints.

  • painting.

  • piping insulation of air lines.

  • electrical equipment installation.

  • control and instrument equipment installation.

  • help in commissioning and test run for the plant.

 

Complete Air System Project

Client: Karbala Gas Power Station

Location: Karbala

Scope:

  • erection.

  • installation.

  • start-up.

  • commissioning of oil free compressors with dryers, treatment unit, cooling tower and Linking to DCS.

  • training.

 

Complete Compressor Package Project

Client: Basrah Gas Company (BGC)

Location: Basrah

Scope:

  • engineering.

  • procurement.

  • packaging.

  • installation.

  • start-up.

  • commissioning of 30 x Skids compressor package with dryers, and all accessories.

Gas Compressor Project

Client: Taji Power Plant (GRS)

Location: Taji

Scope:

  • installation

  • erection

  • start-up

  • commissioning

of (3xSC-10) gas compressors and of fuel gas supply.

Fuel Gas System

Client: Hilla Power Plant

Location: Hilla

Scope:

  • skid supply 

  • installation

  • start-up

  • commissioning

of fuel gas supply system.

Instrument Air Project

Client: State Co. for Mechanical Industries (SCMI)

Location: Baghdad

Scope:

  • engineering

  • procurement

  • installation

  • start-up

  • commissioning

of oil free compressors, cooling towers, treatment unit and electrical links.

Portable Air Compressor Project

Client: ENI Basrah

Location: Basrah

Scope:

  • procurement

  • skid packaging

  • installation

  • start-up 

  • commissioning 

of 6x portable compressors with dryers and automatic controlling for Oil & Gas applications.

Gas Compressor - EPC

Client: South Gas Company (SGC)

Location: Basrah

Scope:

  • engineering.

  • procurement.

  • civil work.

  • installation.

  • start-up.

  • commissioning.

 

 

EPC: 2x gas compressors included civil work, piping, electrical, control, optical cable, and all required accessories.